Sturrock Shipping

Massive infrastructure projects for Port of Durban

Massive infrastructure projects for Port of Durban

Transnet National Ports Authority (TNPA) has embarked on a massive boost to the provision and upgrading of infrastructure at the port of Durban.

DurbanPort1
Maydon Wharf 12 where work has already commended on deepening the berth from its current -5.5m to -14.5m. (Picture courtesy TNPA)

On Monday we reported that investment worth R10.73 billion was underway, and highlighted that some of these involved the deepening of berths 203 to 205 on the North Quay of Pier 2, Durban Container Terminal.

Among the other projects underway is the reconstruction of the Island View petrochemical and oil berths, which have become inadequate in the face of modern shipping and the larger vessels. In addition the berths are ageing and in some cases require complete rebuilding of the dolphin berths.

Island View handles about five million tonnes of oil and petroleum products each year and has a high strategic value to the country, including having a connection to the oil pipelines that run from Durban to the Gauteng area.

Reconstruction of the berths began with berth 6 which has since been fully re-commissioned, with the construction team moving to berth 5. Each rebuilt berth will be 300m in length and capable of handling ships of up to 45,000-dwt in future. The project involving these two berths is worth R363 million.

Reconstruction of berth 2 is also underway and involves a new deck on pile structure for the provision of a third dolphin berth to provide additional length, with the draught alongside being increased from 10.9m to 14.5m CD. This will enable tankers of up to 60,000-dwt in size to use berth 2. This project is costing R263 million and is due for completion in March 2012.

One of the major and most exciting projects in the port involves the historic Maydon Wharf area, where TNPA has undertaken to rebuild seven of the 15 berths while deepening them at the same time. Costing R1.6 billion the project will see berths 12 - 14 and berths 1 - 4 being deepened using sheet pile quay walls to provide a draught alongside of -14.5 metres and to handle ships of up to 65,000-dwt.

Work has already commenced on berth 12 - the contractor Stefanutti Stocks moved on site in July and the entire project will be complete by July 2016. One might expect that a further contract to attend to the remaining berths might then follow.

Port manager Ricky Bhikraj says that one of the key areas that TNPA faces is how to manage the logistics around the rejuvenation of the berths while the reconstruction of each berth is taking place. Cargo working that is displaced has to be accommodated elsewhere.
The area between berths 9 and 13 is likely to become a new stand-alone container terminal once the berth deepening is complete. Container ships have already begun using berths 10 and 11 for this purpose.

Other projects involving Maydon Wharf include back of port operations. A large number of non-port related activities take place within the 120ha precinct and TNPA is in discussion with these firms to encourage them to relocate away from the harbour so that port spaces can be utilised for import/export activities instead.

This may take a number of years to bring to fruition but in the meantime the road and rail system within the area will also undergo rejuvenation, with the redesigning of Maydon Road to include adjacent truck staging areas. This is to alleviate the chronic road congestion along Maydon and Johnson Roads as heavy-duty vehicles arrive from upcountry to load or discharge grains, minerals and chemicals. As they can only access the respective terminals two or three at a time it forces other arriving vehicles to wait on the roads outside, resulting in traffic congestion.

Meanwhile work on widening and realigning the Bayhead Road beyond the turnoff to Durban Container Terminal Pier 2 is continuing and several new truck staging areas are also being prepared. A further project beyond this involves the building of the talked-about link road connecting the container terminals on Piers 1 and 2 with Edwin Swales VC Drive to the south, to alleviate some of the heavy traffic from Bayhead Road.

DurbanPort2
Panoramic view of Maydon Wharf looking across berths 7 on the right, to 11 on the left, with berths 12 to 15 around the corner. The narrow Maydon Channel is also visible. (Picture courtesy TNPA)

Other projects for Durban include the construction of a new passenger terminal on A berth along with new administration buildings, but that can be dealt with in a future report.

Good news for the people of Durban however was that the North Pier, which provides some of the best views across Durban's famous Golden Miles of beachfront and holiday-land, is due to be reopened to the public from June 2012. That's according to the port manager who said that all that remained to be settled was the question of road traffic flows and parking, and the provision of suitable railings along the pier.

 

Source: Ports and shipping - Terry Hutson